Crenshaw/LAX Transit Corridor: Simcoe Street Train Station Tunnel

Crenshaw/Los Angeles, CA
Role: SOE Design of Stations; Design Build for Contractor

Client: Walsh-Shea Constructors
Construction Cost: $1.27 Billion

 

Technology: Cut and Cover
Geology: Soft Ground; Young and Old Alluvium

 

Dimensions: 3 stations, each 806 x 110 ft (245 x 33 m) – 70 ft (21 m) diameter
Length: 13,728 ft (4 km)
Depth: 67-71 ft (20-21 m)

 

Project Elements

Previous
Next

Westside Purple Line Extension, Phase 2: Rail Transit Line

Beverly Hills (Los Angeles), CA

Role: Tunnel Design Lead; Design Build for Contractor

Client: STV Inc.
Construction Cost: $6.3 Billion (3 phases)

 

Technology: EPBM
Geology: Soft Ground

 

Dimensions: 18.8 ft ID (5.7 m)
Length: 2.2 mi (3.5 im)
Depth: 50-70 ft (15-21 m)

 

Project Elements:

Previous
Next

Innovative, cost-effective, practical solutions and designs driven by Client’s needs.

Atlanta Airport Plane Train Turnback Tunnel

Atlanta, GA
Role: Owner’s Engineer for tunnel and Access Shaft; Progressive Design Build

Client: Ricondo
Construction Cost: $140 Million

Technology: SEM, Drill and Blast
Geology: Soil/Rock

Dimensions: 22 ft (6.7 m); Tunnel bifurcation up to 48 ft (14.5 m) span

Length: 780 ft (237 m)
Depth: 36-55 ft (11-17 m)

 

Project Elements: 

Previous
Next

Alaskan Way Viaduct Replacement Program

Seattle, WA
Role: Cost and Risk Verification Check and Expert Review Panel Member

Client: Washington State DOT
Construction Cost: $3.1 Billion

 

Technology: EPBM and Cut and Cover
Geology: Soft Ground

 

Dimensions: 58 ft (17.6 m)
Length: 9600 ft (2.9 km)
Depth: 20-50 ft (6-15 m)

 

Project Elements: 

Previous
Next

Westside Purple Line Extension, Phase 3: Rail Transit Line

Westwood (Los Angeles), CA
Role: Tunnel Design Lead; Design Build for Contractor

Client: STV Inc.
Construction Cost: $460 Million

 

Technology: EPBM
Geology: Soft Ground

 

Dimensions: 20.3 ft ID (6.1 m)
Length: 2.6 mi (4.2 km)
Depth: 50-70 ft (15-21 m)

 

Project Elements: 

Previous
Next

Montreal Airport Station, Transit Terminus for REM

Montreal, QB
Role: Tunnel, Shaft and Station cavern Design – Precast Concrete Liners, Connections and Complex Fault Crossings

Client: Aeroports de Montreal

Construction Costs: $600 Million

Technology: Drill and Blast

Geology: Rock

 

Length: 815 ft (250 m)

Diameter: 31 ft (9.6 m) with 79 ft (24 m) span cavern

Depth: 86-142 ft (26-43 m)

Project Elements

Olentangy Augmentation Relief Sewer (OARS)

Columbus, OH
Role: Construction management, technical support

Client: City of Columbus
Construction Cost: $375 Million

 

 

Technology: EPBM/Slurry TBM
Geology: Karst limestone

 

Diameter: 20 ft (6 m)
Length: 23,000 ft (7010 m)
Depth: 200 ft (50 m)

 

Project Elements: 

Previous
Next

Rebecca Trunk Wastewater Main

Oakville, ON

Role: Microtunnel Designer & Construction Inspection/Administration

Client: Cole Engineering

Construction Costs: $43 Million

 

Technology: Drill and Blast

Geology: Rock

 

Length: 2,476 m & 1,575 m

Diameter: 1,200mm (48 in) & 1,350mm (54 in)

Depth: 14 m (46 ft)

 